SPS were awarded the contract to install 212 contiguous piles for a new apartment development in Poole, forming a close-spaced pile wall to support the excavation.
Client
Woodmace Concrete Structures Ltd
Location
30 tower Road, Poole BH13 6HZ
Sector
New Apartment Development
Services
Scope
212 no. 350mm diameter CFA retaining wall piles 8.1m deep
Overview

Value: £91k

Specialist piling was awarded the contract to install 212 contiguous piles for a new apartment development in Poole. Contiguous pile walls (cast in-situ bored or CFA) – this wall method is often used in permanent applications. Structural piles are installed at close spacing’s typically with a 100mm gap between piles. The soil is therefore exposed during excavation but will often self-support temporarily due to “arching”.

This method is suitable in a variety of soils where groundwater lies below the maximum excavation depth.

Project Gallery

Related projects

‘Pastures’, University of Essex

Specialist Piling Solutions delivered 685 CFA bearing piles across five plots, with a further 28
Find out more

Riviera Hotel, Bournemouth

Following the demolition of the former Hotel Riviera, this development created 14 new apartments with
Find out more

Okeford Fitzpaine

With planning approved for up to 45 new homes, SPS installed 521 Steel-Case Driven piles
Find out more

Want to see more projects?

Explore nationwide foundation and structural retaining walls engineered to strict municipal regulations.

Discuss a site, scheme or challenge

Our team is ready to help you find the right piling or foundation solution.